Mt Gravatt Private Hospital

Client: CBA Health/MGPH

Value: $9.2M

The brief.

MDB was engaged to manage the project on the client’s behalf, from design development through to construction.

Our approach.

We procured the design team and coordinated the design to 70 per cent design development. We then ran the procurement of the builder for the client, and managed the project through construction, working alongside the client’s health consultant and the builder.

The result.

MDB managed the nominated builder from project commencement to completion, and MGPH was constructed and completed ahead of the contract programme date.

“Matt led his team to complete Australia’s first 5-star, green star aged care facility in Carseldine on time and within budget, a real professional.”

Melissa Argent / CEO, Rockpool

Related Projects

Multi-Residential

Caloundra, QLD

2027

Canberra Terrace, Caloundra

CLIENT: BOB. Out of the Box

A coordinated design team taking a new residential building from concept through development approval, with construction due to start in early 2027.

DELIVERY ROLE

Builder/Developer

$12.5M

Industrial

Geebung, QLD

2026

Geebung Factory Extension

A redesigned suspended slab removed the need for site excavation, lowering the price and delivering the extension in around four months.

DELIVERY ROLE

Head Contractor

$1.1M

Commercial

Gympie, QLD

2026

Anglican Church Parish Centre

CLIENT: Anglican Church Gympie

Three rounds of value engineering brought an over-budget tender within reach. Delivered on time: parish office, commercial kitchen, conference room and accessible grounds.

DELIVERY ROLE

Head Contractor

$1.2M